(1) The demand for rectifying the defects, the claim for damages, or the rescission of the contract mentioned in Articles 667, 668 and 669 shall be made within one year from the day of the delivery of the subject-matter of the work.
(2) Where the delivery of the subject-matter of the work is not required, the period mentioned in paragraph (1) shall commence to run from the day on which the work was finished.